Tentative Design Schedule

  • Conceptual design (20% complete) –  4/2017
  • Preliminary design (65% complete) – 7/2017
  • Pre-final design (85% complete) – 9/2017
  • Final design (100% complete) – 11/2017
  • Final design complete 12/2017

Tentative construction timeline

  • Construction award 3/2018
  • Construction start 4/2018
  • Construction complete 4/2019

Additional public meetings will be announced in 2017.