Tentative Knox St. Complete Streets Schedule

03 Thursday Nov 2016

Posted by Mark R. Brown in Knox Street Complete Streets Project

≈ 1 Comment

Tentative Design Schedule

  • Conceptual design (20% complete) –  4/2017
  • Preliminary design (65% complete) – 7/2017
  • Pre-final design (85% complete) – 9/2017
  • Final design (100% complete) – 11/2017
  • Final design complete 12/2017

Tentative construction timeline

  • Construction award 3/2018
  • Construction start 4/2018
  • Construction complete 4/2019

Additional public meetings will be announced in 2017.

Tyler & Polk Two Way Conversion Project

02 Wednesday Nov 2016

Posted by Mark R. Brown in Tyler Polk Two Way Conversion

≈ Leave a comment

Dallas City Planning Commission recently approved a proposal to convert Tyler Street and Polk Street between Canty Street and Pembroke Ave from one way to two way operation. The proposed complete street project will improve quality of life by slowing traffic speeds and providing a potential bike lane on Polk Street.

The PowerPoint from the July 2016 public meeting can be viewed here. For additional information, please contact Kimberly Smith, Senior Planner, Mobility and Street Services Department (kimberly.smith@dallascityhall.com).

More information about the project can also be found on Councilman Scott Griggs project website.

 

McKinney & Cole Two Way Conversion

02 Wednesday Nov 2016

Posted by Mark R. Brown in McKinney and Cole Two Way Conversion

≈ Leave a comment

The City is in the conceptual planning stages of converting McKinney & Cole Ave. from one way to two way from Allen Street to Harvard Ave. The two-way conversion of McKinney and Cole Ave. supports the vision of the Dallas Complete Streets Manual by slowing traffic through residential & commercial neighborhoods, potentially reducing the number and severity of crashes for all modes, and improving the convenience and ease of use of our streets.

While bike lanes will not be included in this project, slower traffic speeds and improved neighborhood navigation due to the two-way conversion will encourage more cyclists to use McKinney and Cole for recreation and commuting throughout Uptown.

The PowerPoint presentation from our August 2016 public meeting can be viewed here. Additional public meetings will be announced in 2017. For information about the project, please contact Kimberly Smith, Senior Planner, Mobility and Street Services Department (kimberly.smith@dallascityhall.com)

More information can also be found on Council Member Philip T. Kingston’s website.

 

Categories

  • Cedar Springs Complete Streets Project
  • Commerce St. Complete Streets Project
  • Henderson Ave. Complete Streets Project
  • Knox Street Complete Streets Project
  • McKinney and Cole Two Way Conversion
  • Tyler Polk Two Way Conversion
  • Uncategorized

Dallas City Links

  • Dallas City Website
  • Dallas Complete Streets Design Manual

Archives

  • May 2017
  • November 2016
  • December 2015
  • September 2015
  • April 2015
  • March 2015
  • December 2014
  • November 2014
  • September 2014
  • August 2014
  • May 2014
  • April 2014
  • March 2014

Meta

  • Register
  • Log in
  • Entries feed
  • Comments feed
  • WordPress.com

Dallas City Links

  • Dallas City Website
  • Dallas Complete Streets Design Manual

Blog at WordPress.com.

Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy